Coming off our Monthly Production Planning Conference call the TM-1 schedule has been revised
slightly to meet Subway basesheet needs between now and Tuesday night
Here’s the revised plan
- Run a truckload of GBC Gr105 – will be complete within the hour
- Run a combination of two 29-7/8” and one 33-7/8” truckloads to service HPC-Hattiesburg immediate needs
- Go back to GBC Gr 105 and produce 90 tons
- Run 6 to 7 truckloads of Gr 314 to assure un-interrupted basesheet supply of Subway Gr 314
- Go back to GBC Gr 105 and produce an additional 90 tons
- Run Grade 301 104” trim into the PM day on Tuesday